Upgrade the Jabulani precinct in Soweto
AI draft.Drafted by AI from the livestream; the quote below is what was said. Use the timestamp to check it before you quote it.
No dateDada Morero · Executive Mayor
Official record: SDBIP 2026/27, JDA Q2 2025/26 report (AI-matched)
01:11:587 May 2025· R24.2 million· Report an error
Latest: Said in progress at a later sitting, 27 May 2026 (AI judgment)
Deadline: none given.
Evidence: quote · 1 later sitting · official record (4)
“The Jabulani precinct upgrade with a 24.2 million allocation under development planning”
- In progressBudget speech: roads, inner city and township renewal · 27 May 2026
- Official record SDBIP 2026/27, p.116: “Jabulani Precinct Upgrades” · R 15,000,000 (2026/27); R -; R -Plan for July 2026 to June 2027; online since Monday, 1 June 2026. AI-matched, not yet checked by a person.
- Official record JDA Q2 2025/26 report, p.69: “Jabulani Precinct Upgrades” · Stage 5: Construction · Due completion 28 November 2025 · R 24 234 000.00 (2025/26)October to December 2025; online since Wednesday, 4 March 2026. AI-matched, not yet checked by a person.
- Official record JDA Q2 2025/26 report, p.69: “Progress completion is 90” · Progress completion is 90%; contractor unable to expedite due to delayed payment by JDA · Due completion 28 November 2025October to December 2025; online since Wednesday, 4 March 2026. AI-matched, not yet checked by a person.
- Official record JDA Q2 2025/26 report, p.125: “Jabulani Precinct Upgrades” · 77.41% used; actual R17 985 841 · R 23 234 000 (2025/26 annual budget)October to December 2025; online since Wednesday, 4 March 2026. AI-matched, not yet checked by a person.
All promises · Watch it at the sitting, with the transcript
Overdue means the date has passed and nothing we found says it was done; it is not proof it wasn't. How promises are found and counted: Promises.